Four Ready-To-Build Parcels
Adjacent to Established Neighborhood. Rail Access.
Work is beginning to convert William Stanley Business Park Site 9 into four ready-to-build parcels, complete with roadways, green spaces, utility corridors, and stormwater management. This 16.5-acre site contains four parcels that are ideal for industrial, manufacturing, commercial uses, and retail. Site 9 includes rail access. This green site will integrate beautifully into the adjacent, well-established Tyler St. neighborhood, complete with shops, restaurants, banks, and housing options. Your employees can walk to almost everything they need.
See the image below to learn how the space is being redeveloped:
Current Status
December 29, 2023 – William J. Keller & Sons Construction Corporation of Castleton, N.Y., was unanimously chosen by the Pittsfield Economic Development Authority to oversee the $10.8-million renovation. Keller, a union shop, plans to hire workers and sub-contractors from Berkshire County. Keller’s previous experience includes the Clark Art Institute in Williamstown. (see Berkshire Eagle)
February 16, 2023 – The Pittsfield Economic Development Authority raised the entire $10.8 million that it expects to need to redevelop Site 9. Funds include:
- $4.5 million from the federal American Rescue Plan Act (ARPA) awarded by the City of Pittsfield.
- $3 million from MassWorks
- $1.3 million from the GE Landscaping Fund
- $880,000 Site Readiness grant from MassDevelopment
- $500,000 Economic Development Earmark
- $260,000 Brownsfield grant
Transforming Site 9
September 10, 2024
August 13, 2024
July 3, 2024
May 3, 2024
February 5, 2024
February 5, 2024